MasterGlenium SKY 903 was used in world’s largest underwater concrete pour. This product was specifically engineered to allow high levels of water reduction and very long workability retention, without sacrificing early strength development performance.

The biggest single pour for the South Tower foundation, resulted in 16,869m3 of concrete being produced and delivered without any delays or returned concrete and was tackled in a non-stop process, 24 hours a day, over 15 days which, at its peak, involved up to 100 people.

Details

Published 25/04/2017

Subjects

CI/SfB subheadings under which this case study is classified: