Home > Companies > ARDEX UK Ltd
It’s a ‘race to the finish,’ as ARDEX UK complete Commonwealth Games Pool refurbishment in 8 weeks

It’s a ‘race to the finish,’ as ARDEX UK complete Commonwealth Games Pool refurbishment in 8 weeks

Case Study
The 2014 Commonwealth Games’ swimming competition was played out at Tollcross International Swimming Centre. In anticipation of the games, the centre’s facilities underwent a complete refurbishment. Some of the screed below the tiles on the main competition pool floor had separated from the concrete pool tank. The entire floor needed to be re-laid. Glasgow City Council Scott hired, Tilecraft, a specialist tiling works company that delivers high quality tiles, to lay the tiles and specified products from ARDEX UK. A fast track solution which would produce high quality results was needed, and ARDEX UK seemed the logical choice.

Details

Published 05/03/2015

Subjects

CI/SfB subheadings under which this case study is classified: