Upper Dolfor Road

Upper Dolfor Road

Case Study
A self-build, six-bedroom, detached
property, in Powys. Using aircrete, a certified MMC, main contractor B.W Bellis was able to complete the block-work within six weeks. Apart from some
technical assistance from H+H on
working with aircrete, all of the block
work was laid by a single worker
during this time. The main contractor had used H+H Celcon Blocks when building his own home and was impressed with the thermal performance so recommended the use of aircrete to the client. Products used: Celcon 140mm Jumbo Bloks on the inner leaf cavity walls of the property.